DETAILS OF WORK UNDER
WATER SUPPLY SECTOR
BPL/WS/01: Supply, Installation and
Maintenance of Electromagnetic Flow Meters, Clamp on Ultrasonic Flow Meters
and Bulk Consumer Meters.
•
13 Nos. Electromagnetic Meters at Raw Water and Clear Water
Pumping Stations
•
2 Nos. Portable Ultra sonic clamp on type Meters
•
Meter reading and Maintenance for 2 years
•
Training to BMC staff
BPL/WS/02
: Rehabilitation of existing Raw Water Pumping Stations, Clear Water Pumping
Stations, replacement of Rising Mains around Upper Lake.
•
Rehabilitation of Yacht Club-I, Yacht Club-II, Karbala,
Bairagarh, Kamla Park Raw Water Pumping Stations including all civil, mechanical
and electrical works.
•
Rehabilitation of Shyamla 2.0 MGD, Bairagarh Clear Water
Pumping Stations including all civil, mechanical and electrical works.
•
Replacement of raw Water pumping main for Arera WTP and
BHEL WTP.
BPL/WS/03 : Rehabilitation of 7 Water Treatment
Plants around Upper Lake.
Rehabilitation of Shyamala 4.5 MGD,
Shyamala 2.0 MGD, Bairagarh 1.0 MGD, Idgah 3.0 MGD, Arera 5.0 MGD, Badal Mahal 1.0
MGD, Pulphukta 3 MGD WTP including all civil, mechanical and electrical works.
BPL/WS/04 : UFW reduction in a Pilot Area (Koh-E-Fiza).
•
Bulk metering and consumer metering in Pilot Area (about
2500 connections).
•
Leak Detection and Repairs. (Acceptable limit 15lits/connection/hour).
•
Repairs replacement of below 100 mm dia pipe lines.
•
Replacement of service connections.
BPL/WS/05 : Leak detection and rectification in pipelines of
300 mm diameter and above
•
Repairs of all visible leakages.
•
Detection of hidden leaks using leak detection equipments.
•
Repair of detected leaks.
•
Training to BMC staff.
BPL/WS/06 : Supply, laying and
testing of distribution & feeder man mains of 100-450 mm dia. App. 80
Km.
•
Rehabilitation of distribution system and expansion
in Gandhi Nagar, Vijay Nagar, One Tree Hills.
•
NehruNagar and CTO areas in ward 1, 2, 3, 4.
BPL/WS/07 : Supply, laying and testing
of distribution & feeder man mains of 100-450 mm dia. App. 80 Km.
• Rehabilitation of distribution system and expansion in Harshwardhan
Nagar, Nehru Nagar, Kotra Sultanabad, Aradhana Nagar, Ambedkar Nagar, Sudama Nagar,
Chitragupt Nagar, Vaishali Nagar, Dwarkapuri, Kotra Govt. Qtrs., Naya Basera.
•
Rehabilitation of distribution system in 1100 qtrs.,
E-5, E-6, E-7 Arera and Shahpura Chaoni Areas.
WS-08 : Supply, laying and testing
of distribution & feeder man mains of 100-450 mm dia. App. 80 Km.
•
Rehabilitation of distribution system in Ward 23,24,
25 and Ashoka Garden areas.
•
Rehabilitation of Feeder main in Ward 36 and 37.
BPL/WS/09 : Construction of Service Reservoirs and
Sumps.
•
Vijay Nagar -ESR -1.0 ML, Ambedkar Nagar
-ESR-2.25 ML.
•
Nehru Nagar -ESR-2.25 ML, Kotra Sultanabad- ESR - 2.25
ML.
BPL/WS/10 : Construction of following Service Reservoirs.
•
Kho e fiza -ESR- -1.0 ML,City Kotwali –ESR
-3.0 ML.
•
Shahpura – ESR-2.0 ML,Professor Colony- ESR- 1.0
ML.
BPL/WS/11 : Transmission mains.
•
DI Pipes 350 mm to 500 mm dia to feed New Service reservoirs
(Approximate Length-13 Km.).
BPL/WS/12 : Bulk Consumer meters.
•
Mechanical Meters to Bulk Consumers.
•
1905 Nos. Mechanical meters for Bulk Consumers.
BPL/WS/13 : Rehabilitation of Clear Water Pumping Stations(Phase
II) .
Rehabilitation of Pullpukhta, Badal Mahal and Arera
Clear Water Pumping Stations including
replacement of all pumping plants.
DETAILS OF WORK UNDER WASTE WATER AND
SANITATION SECTOR
BPL/WW/01 : Sewer network in Gandhinagar, Mohali, Kotra
zones. Augmentation of lateral.
•
Area : Ward no 4,5,6,9,23,25,26,19,31,37,43 and 44.
BPL/WW/02 –Lot-I : Laying sewers to prevent pollution of Upper
Lake .
Laying Sewer lines &
construction of main holes etc. in following areas:
•
Ward no. 3, 4, 5, 6, 7, 23, 26, 27, 28, 29, 31.
•
Koh-e- fiza, Ahemdabad housing board and BDA colony, NRI colony, 4 quarters etc
to minimize pollution of Upper Lake through Sirin Nala.
•
Rajendra Nagar slum, Indra Nagar Slum, Bairagarh etc.
•
Kotra, Ginorri area etc.
•
Shahid Nagar, Garam Gadda, Fathegarh, Sadar Manzil, Medical
Hostel etc.
•
Some areas of Shymla Hills, Nadir colony etc.
BPL/WW/02 Lot-II : Sewer System in Old Bhopal Area.
Laying Sewer lines
& construction of main holes etc. in following areas:
•
Ward no. 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18,
19, 20, 21, 22, 24.
BPL/WW/04 : Additional works of Existing
25 Mld Sewage Treatment Plant at Maholi Dhamkheda.
•
Details –Construction of effluent channel and other allied
works.
BPL/WW/05 : Sewage Pumping Station and Pumping main.
•
Details- Estimated Capacity 32 Mld.
•
Location-: Old Bhopal Area.
•
Pumping main -: 700 to 900 dia DI Pipe ,Length Approximately
– 5 Kms.
BPL/WW/06 : Construction of Public Toilets (25 Sets).
•
Type A : Each with 15 Seats , Type B: Each with10
Seats.
PMU/WW/01 : Procurement of Sewer
Suction cum Jetting, Suction and Jetting machine of various capacities.
DETAILS OF WORK UNDER SOLID
WASTE MANAGEMENT SECTOR
BPL/SWM/03 : Development of two
new Sanitary Landfill sites including all civil works and operation of landfill
sites for one year.
Details-
•
Locations : Fatehpur Dobra,
Adampur Chaoni.
•
Site infrastructures like entrance gate, watchman’s cabin,
compound wall, approach road, weigh bridge record room, office building, green belt,
toilet/washing facilities, fire protection system, leachate collection system, drains,
including electrical works, water supply and sanitation works.
•
1 no. weigh bridge.
•
Area of land available at Fatehpura Dobra and Adampur Chaoni
is 60.95 acres and 44 acres respectively.
BPL/SWM/01 : Supply of Dumper trucks,
Bull dozers, Excavator cum loaders and front-end loaders for operation of Landfill
sites.
BPL/SWM/02 : Supply of 1m3 containers, 4.5m3 containers, Refuge
compactors and Dumper placers for secondary collection.
BPL/SWM/03 : Supply of containerized wheel Barrows, tricycle,
for primary collection etc.