• Home (current)
Mpudc MPUSIP ADB AF Progress
 laying work of HDPE Pipe 90mm, Barela – 5E
laying work of HDPE Pipe 90mm, Barela – 5E
Excavation works at Anicut, Bada Malhera – 6K
Excavation works at Anicut, Bada Malhera – 6K
Road Restoration, Bada Malhera – 6K
Steel binding work of Filter House, Gohad-4C
HSC works, Khargapur-6J
Steel Binding and Shuttering Work at WTP, Harpalpur – 6G
Reinforcement binding work at footing mesh of sludge drying bed foundation, Baihar - 5H
shuttering work at WTP, Harpalpur – 6G.
Shuttering work at lateral vertical wall of sludge drying bed, Malajkhand – 5H
Reinforcement checking at 800kl OHT, Joura – 4G
Brick work at boundary wall, Lora OHT, Malajkhand – 5H
Water Meter Installation Work in Progress in Hatta (Contract Package 6D)
Shuttering work at vertical wall of sludge collection chamber of CLF, Malajkhand – 5H
Shuttering work at Chinditola OHT, Malajkhand – 5H
Road Restoration, Patera – 6L
CLF container wall casting work, Vijayaraghvgad – 5D
Road Restoration, Jeron khasla – 6H
walkway shuttering work at WTP, Harpalpur – 6G
Approach Bridge of Intake well, Harpalpur – 6G
Shuttering work of 650 kl OHT, Gohad – 4C
Trench Excavation Work for HDPE Pipe, and Water Level Status at WTP, Bada Malhera – 6K
Trench Excavation Work for HDPE Pipe, and Water Level Status at WTP, Bada Malhera – 6K
Shuttering work of 4th lift of 1120 kl, Gohad – 4C
Door to door verification, Gadhi Malhera – 6M

© 2019 MPUDC All rights reserved | Design by MPUDC