Mpudc MPUSIP Phase-I Progress
Summary of Schemes & Towns Covered Under MPUDC - Month December-2023 | ||||||
S.No | Project | Funding Agency |
Sanctioned Projects No. of ULBs |
Projects in Progress No. of ULBs |
Average Progress Physical |
Average Progress
Financial |
1 | Water Supply | ADB Phase I Funded | 64 | 64 | 92.50% | 92.34% |
2 | Sewerage | ADB Phase I Funded | 4 | 4 | 49.75% | 49.54% |